22.10.2018 - the builder has officially started onsite. Demo is completed.
30.10.2018 - plumbers digging out the drains, breaking through the rock.
15.11.2018 - underground plumbing is complete, formwork and slab preparation is now underway.
23.11.2018 - formwork + slab structural steel underway with the slab pour expected early next week.
07.12.2018 - slabs are completed and the framing has started.
12.12.2018 - framing is well and truly underway, finishing the year out onsite like a steam train.
20.12.2018 - first floor framing is done. Posi struts first cab of the rank in the new year.
16.01.2019 - windows are in, the steel is being installed n the brickies are underway.
23.01.2019 - brickies are done, first floor frames set to commence next week.
12.02.2019 - posi struts are in, second floor works are underway.
21.02.2019 - the first floor flooring is down and the first floor frames are about to go up.
27.02.2019 - first floor frames are almost up.
13.03.2019 - first floor frames are done and the roof trusses are on. Next comes the roofing.
26.03.2019 - work underway on the roof detail. Scaffolding going up in prep for external cladding.
03.04.2019 - Scaffolding is up ready for the external cladding which is expected to stat tomorrow.
11.04.2019 - Roofing detail and external painting underway.
24.04.2019 - the roofing is on, all but finished. Second floor external cladding underway.
21.05.2019 - internal fix underway, plastering within the next week or two.
12.06.2019 - second floor rendering complete and internal rough in almost complete.
24.06.2019 - internal rough in all but complete, external painting underway.
11.07.2019 - internal plastering complete, facade all but complete only painting to go.
19.08.2019 - Tiling and joinery well underway.
02.09.2019 - Fit-off started, painting looking good, joinery and stone complete.
11.09.2019 - Timber flooring is underway, new fencing complete and landscaping up next.
26.09.2019 - front paths have have been concreted, landscaping all but done and final internal fit off and commissioning is underway.
09.10.2019 - in the last week. All buyers expected to receive keys to their new dwellings early next week.