30.08.2020 - Demolition is now complete. Construction to start shortly.
26.10.2020 - Drains complete and slab to start next.
09.11.2020 - Slab form work in progress and pouring concrete soon.
03.12.2020 - Ground floor frame and structural steel works underway.
17.12.2020 - Second-floor frame almost finalised, bricklayer to start next.
21.01.2021 - The second-floor frame is complete and all windows are installed. Brickwork in progress.
04.02.2021 - External cladding on ground-floor complete. Roof cover and external lock up next.
18.02.2021 - Scaffolding installed, roof and external lockup in progress.
04.03.2021 - External lockup complete, internal lockup and rough-in to be completed soon.
18.03.2021 - Internal lock-up and rough in's complete and insulation is in progress.
01.04.2021 - Insulation & plaster install is complete and waterproofing is progressing well.
15.04.2021 - Exterior finishes are progressing well and painting to start next.
29.04.2021 - Internal painting and vanity installation complete and tiling is in progress.
13.05.2021 - Tiling; electrical fit off complete and heating/cooling fit off & front fence footing is in progress.
27.05.2021 - Front fence footing; heating/cooling fit off are complete and flooring is progressing well.
10.06.2021 - Carpet and wooden flooring is complete and external decking is in progress.
24.06.2021 - External decking, alfresco joinery and stone works finished & internal painting in-progress.
08.07.2021 - Final internal finishes and installation of front crossovers in progress.
22.07.2021 - Crossover is complete, landscaping has begun and final internal finishes are being completed.
06.08.2021 - Landscaping and final internal finishes are completed. 
19.08.2021 - Council inspection completed and finalisation of subdivision in progress.
02.09.2021 - Statement of Compliance is issued and plans are being lodged to the Titles Office.
16.09.2021 - Awaiting for seperate titles for the units to come through.