16 Elimatta Road, Carnegie

elimatta facade

Carnegie is a popular south-east suburb situated 12km from the Melbourne CBD that is known for it’s ‘eat street’ shopping precinct with cafes and restaurants lining Koornang Road from Dandenong Road to Neerim Road.

The project is currently in the early stages of the town planning process with the proposed development consisting of two exceptionally designed 4 bedrooms, 3 bathroom dwellings including lockup garages, spacious open plan living downstairs and huge retreats upstairs.

16 Elimatta Road is another dual occupancy project in the books. See below for completion images, progress shots and construction updates depicting the entire process.

Completion Video

Completion Images

elimatta kitchen
16 elimatta living
living
bathroom
bedroom 1 elimatta
16 elimatta bedroom
elimatta bbq
16 elimatta facade
elimatta facade
elimatta facade 3
elimatta facade

Renders

16 elimatta road
16 elimatta road living
16 elimatta road bedroom

Looking for property in Carnegie? Check out 14 Wilmoth Avenue Carnegie, another premium dual occupancy project.

Construction Updates

16.09.2021 - Awaiting for seperate titles for the units to come through.

Previous Updates

02.09.2021 - Statement of Compliance is issued and plans are being lodged to the Titles Office.
19.08.2021 - Council inspection completed and finalisation of subdivision in progress.
06.08.2021 - Landscaping and final internal finishes are completed. 
22.07.2021 - Crossover is complete, landscaping has begun and final internal finishes are being completed.
08.07.2021 - Final internal finishes and installation of front crossovers in progress.
24.06.2021 - External decking, alfresco joinery and stone works finished & internal painting in-progress.
10.06.2021 - Carpet and wooden flooring is complete and external decking is in progress.
27.05.2021 - Front fence footing; heating/cooling fit off are complete and flooring is progressing well.
13.05.2021 - Tiling; electrical fit off complete and heating/cooling fit off & front fence footing is in progress.
29.04.2021 - Internal painting and vanity installation complete and tiling is in progress.
15.04.2021 - Exterior finishes are progressing well and painting to start next.
01.04.2021 - Insulation & plaster install is complete and waterproofing is progressing well.
18.03.2021 - Internal lock-up and rough in's complete and insulation is in progress.
04.03.2021 - External lockup complete, internal lockup and rough-in to be completed soon.
18.02.2021 - Scaffolding installed, roof and external lockup in progress.
04.02.2021 - External cladding on ground-floor complete. Roof cover and external lock up next.
21.01.2021 - The second-floor frame is complete and all windows are installed. Brickwork in progress.
17.12.2020 - Second-floor frame almost finalised, bricklayer to start next.
03.12.2020 - Ground floor frame and structural steel works underway.
09.11.2020 - Slab form work in progress and pouring concrete soon.
26.10.2020 - Drains complete and slab to start next.
30.08.2020 - Demolition is now complete. Construction to start shortly.

Progress Shots

Preliminary Drawings

16 elimatta
16 elimatta road
16 elimatta road carnegie

Meet the Builder

The builder for this project is High-End Building and Developments.

high end building

Built upon director John Dean’s foundation of experience bringing over 15 years of experience in Multi-unit development and Townhouse builds to the table.

That knowledge and experience are apparent on every project delivering not only successful outcomes but exceptional experiences.

Location


To learn more about Carnegie click here