04.02.2021 - Demolition complete, demolition waste to be removed and construction starting soon.
18.02.2021 - Construction in progress, with in-ground plumbing work underway.
24.02.2021 - Inground plumbing and civil works underway.
04.03.2021 - Civil works almost complete, excavation works for slab preparation to follow.
18.03.2021 - Excavation works for slab well underway, with slab formwork to follow.
01.04.2021 - Slab work complete.
15.04.2021 - First timber delivery received and framework underway.
29.04.2021 - Garage brickwork and frame in progress.
13.05.2021 - Windows and sliding door installations almost complete, steel frame in progress.
27.05.2021 - Posi struts installation and sub-flooring complete, first-floor framework in progress.
17.06.2021 - Frameworks complete and roof trusses installation in progress.
24.06.2021 - Roof tiles and fascia installation in progress.
08.07.2021 - Roof complete, windows and sliding doors installation in progress.
22.07.2021 - Brickworks complete and first floor external cladding installation in progress.
06.08.2021 - Lockup, roof and rough in complete rendering in progress.
19.08.2021 - Rendering and cladding complete, insulation installation in progress.
02.09.2021 - Insulation installation finalised and plastering well underway.
16.09.2021 - Plastering complete, staircase installation complete and internal prime coat in progress.
30.09.2021 - Site has been closed for two weeks (COVID shutdown) back onsite next week.
14.10.2021 - Tiling and joinery installation in progress.
28.10.2021 - Tiling and joinery completed, driveways and crossover installations are in progress.
11.11.2021 - Driveway and crossover installation complete.
25.11.2021 - Flooring installation on GF complete and plumbers working on fittings installation.
09.12.2021 - Tiling complete and painting underway.
20.01.2022 - Joinery installation complete, skirting and architraves installed and electrical fitting in progress.
03.02.2022 - Landscape complete, carpet and appliances installation in progress.
17.02.2022 - Cleaning and caulking are in progress, the site will be ready for completion walk in the next few days.
03.03.2022 - Defects were rectified and handover is in progress.