23.01.2020 - demolition has been completed and the site set-out is underway.
05.02.2020 - drainage and sanitary piping has been completed. slab formation next up.
19.02.2020 - slab poor is underway.
04.03.2020 - slabs are now completed. Framing to follow.
27.03.2020 - pre-fab frames have been delivered. Erection to start in the next couple of days.
08.04.2020 - ground floor framing and structural steel are both underway.
23.04.2020 - the last of the steel is in. First floor frame underway.
07.05.2020 - first-floor frame complete, ground floor brickwork is underway.
21.05.2020 - second floor frame is underway.
03.06.2020 - roof truss installed and external cladding underway.
17.06.2020 - progressing with the external cladding.
01.07.2020 - internal rough-ins underway.
17.07.2020 - the roof is now complete.
30.07.2020 - sisalation paper is done, battens for cladding is installed. Cladding to start next week.
12.08.2020 - external cladding installation is in progress.
25.08.2020 - cladding going well and rough-in's to start from next week.
10.09.2020 - rough-ins are still in progress and stair measurements are underway.
24.09.2020 - cladding, rough-ins and windows nearly completed and plastering to commence soon.
14.10.2020 - rough-in nearing completion and ceiling battens being installed, ready for plaster.
26.10.2020 - external rendering nearing completion and internal insulation well underway.
12.11.2020 - external cladding and rendering to the rear is complete. Plaster and staircase up next.
27.11.2020 - joinery and staircase in progress and plaster underway.
17.12.2020 - joinery and staircase are almost complete. Scaffold removed and facade close to completion.
21.01.2021 - kitchen joinery complete and staircase framing is progressing well. Tiling to start next.
04.02.2021 - bedroom joinery installed and bathroom tile and bath installed.
18.02.2021 - waterproofing & external plumbing works in progress.
24.02.2021 - service connections in progress and fittings installation complete.
04.03.2021 - stone works and tilling almost complete and painting underway.
18.03.2021 - driveway and stormwater pits complete.
01.04.2021 - boundary fence complete, landscaping and painting in progress.
15.04.2021 - tiles and painting almost complete, garage door and flooring installation next.
29.04.2021 - carpet installation in progress, paint finalised and main switchboard installed.
13.05.2021 - carpet & flooring finalised, paint touch up in progress. Project almost complete.
27.05.2021 - water tank installation in progress and builder rectifying defects.
10.06.2021 - defect works complete, certificate of occupancy to be issued soon.
24.06.2021 - sealing driveway in progress and handover to follow soon.
08.07.2021 - handover process in progress.