13.05.2022 - Received builder's confirmation that they started onsite on 4 May 2022.
26.05.2022 - Footing box out completed.
09.06.2022 - Concrete completed.
23.06.2022 - Slab completed, frame on site.
08.07.2011 - Internal stud walls and structural steel on progress.
22.07.2011 - Posi frame under construction.
05.08.2022 - Upper floor frame work started.
05.08.2022 - Garage structural steel and upper floor timber wall completed.
02.09.2022 - Brick, windows & studio frame completed.
15.09.2022 - Cladding to start and roof to be installed in studios.
29.09.2022 - Cladding works in progress.
13.10.2022 - Cladding works in progress, balcony waterproofing, insulation and plastering to start.
27.10.22 - Colourbond cladding to continue, insulation & plaster to commence.
10.11.2022 - Colourbond cladding in progress, insulation is done & external painting has begun.
24.11.2022 - Cladding to continue and stairs to be installed soon.
08.12.2022 - Cladding and waterproofing underway & stairs are installed.
20.01.2023 - Lower roof works and painting to start.
02.02.2023 - Cladding nearing completion, joinery and painting to continue.
16.02.2023 - Joinery nearing completion, painting to continue.
02.03.2023 - Rendering underway, sewer vent works & gas run in to commence.
16.03.2023 - Sewer vent install complete and remaining cabinetry to continue.
30.03.2023 - Water-tapping, bulkhead and plaster patching, painting all to start.
13.04.2023 - Cabinetry works expected to be completed soon.
27.04.2023 - Cabinetry works & plaster to bulkheads continued, plumber roll overs & painting to start.
11.05.2023 - Plaster bulkhead continued, plumber roll overs, painting and front fence footings to start.
25.05.2023 - Carpentry finishes, pre-paint in progress and painting, fence brick laying to commence.
08.06.2023 - Painting and stone (unit 1) to commence, front fence near complete.
22.06.2023 - Paint works complete and tile and stone installations to commence.
06.07.2023 - Heating and cooling fit off has been completed.
20.07.2023 - Tile and stone installation has been completed.
03.08.2023 - Electrical fit-off complete and timber flooring, carpet & Internal glazing to commence.
17.08.2023 - Carpet, Engineered Timber flooring and internal glazing complete.
31.08.2023 - Completed the internal defects walkthrough and have also completed the external bagging and rendering.
14.09.2023 - There are various trades onsite working through the defects including cabinet makers, painters and electricians.
28.09.2023 - Concrete laneway repairs and epoxy garage floors complete.
12.10.2023 - Final stages before handover, walkthrough planned for this week.
26.10.2023 - PCI items and Pre-Handover Inspection Report items addressed.
23.11.2023 - Project is now completed.