26.02.2021 - Demolition complete, site ready for construction commencement.
03.03.2021 - Site set out underway.
11.03.2021 - Site set out and electrical run complete.
18.03.2021 - Inground plumbing installation in progress, stormwater drainage to follow.
01.04.2021 - Drainage complete, excavation for slab preparation to follow.
15.04.2021 - Slab trench excavation complete and formwork to follow.
29.04.2021 - Slab complete and frame to start next.
13.05.2021 - Garage brickwork in progress, frameworks to start next.
27.05.2021 - Framework on the ground floor in progress and party wall installation to follow.
10.06.2021 - Ground floor frame complete and first-floor frame underway.
24.06.2021 - First-floor frame in progress, roof structure to follow.
08.07.2021 - Framework almost complete, facia and gutter installation in progress.
22.07.2021 - Roof complete and sky lights installation in progress.
06.08.2021 - Facade works in progress, ground floor brickwork complete.
19.08.2021 - First-floor facade works postponed due to COVID-19 restrictions, to resume shortly.
02.09.2021 - Low rear roof trussers installation in progress and first-floor facade works to follow.
16.09.2021 - Scaffold erected and works of FF facade in progress.
30.09.2021 - Site has been closed for two weeks (COVID shutdown) back onsite next week.
14.10.2021 - First floor facade rendering in progress and low roof to be completed soon after.
28.10.2021 - The first floor render wall and cladding completed.
11.11.2021 - Low roof complete and GF cladding installation in progress.
25.11.2021 - Lock-up stage complete, rough-in and plastering to start next.
09.12.2021 - Ducted Heating and Cooling, Plumbing rough-in and external rendering in progress.
20.01.2022 - Builder will resume activities on site next week, completing rough-in and preparing for plastering.
03.02.2022 - Rough-in complete, insulation and plastering to start in the next few weeks.
03.03.2022 - Plumbing finalised and plastering underway.
17.03.2022 - Organising services and infrastructure connections.
31.03.2022 - Completion of carpentry items and QA pre plaster in progress.
14.04.2022 - Pre plaster is almost complete, plaster is scheduled to start soon.
28.04.2022 - Landscaping & fencing preparation in progress, external rendering & roof work to finish soon.
12.05.2022 - Pre plaster complete, insulation installation almost finalised and plastering to start next week.
26.05.2022 - Insulation finalised and plastering in progress.
09.06.2022 - Plastering is in progress, to be completed by the end of the week.
23.06.2022 - Plastering complete, skirting and architrave installation in progress, painting to follow.
08.07.2022 - Skirting and architrave installation complete, painting in progress.
22.07.2022 - Painting complete and joinery installation to start in the next few days.
05.08.2022 - Joinery installation is in progress & stone benches to be installed soon.
19.08.2022 - Joinery installation to complete soon.
15.09.2022 - Joinery, stone & tiling completed.
29.09.2022 - Fixtures and fittings are installed.
27.10.2022 - Crossovers are being done.