12.12.2018 - demolition is complete and construction is about to start. Aiming for the drains to be done this side of Christmas with the slab to be poured first thing in the new year.
20.12.2018 - construction has started on site, the drains are in and the slab is booked for first cab off the rank in the new year. Here we go!
06.02.2019 - slab preparation all but complete, reo and boxing to follow with the slab booked to be poured next week.
15.02.2019 - the slab is down, the framers are locked in for next week.
21.02.2019 - framers are onsite and the first floor framing is underway.
05.03.2019 - first floor frame is done, roof trusses have been ordered.
20.03.2019 - garages have been bricked up, first floor steel about to go in. Trusses have been ordered.
01.04.2019 - ground floor steel has been installed. Chippies back onsite installing windows tomorrow.
12.04.2019 - the windows are in and the ground floor brickwork is underway.
24.04.2019 - the posi struts are installed and the first floor flooring has been delivered ready to be installed.
06.05.2019 - first floor flooring is down and the framing is underway.
12.06.2019 - roofing and guttering complete, second floor brickwork underway.
24.06.2019 - the aircon rough in is complete, electrical rough is about to kick off and second floor brickwork is all but complete.
11.07.2019 - brickwork complete, rough in complete and plastering to come.
18.07.2019 - the insulation is all in, the plastering is underway and the top floor external works are complete.
19.08.2019 - Plastering complete, tiling and joinery well underway.
11.09.2019 - joinery complete, painting looking good. Fit-off under way with landscaping set to start in the next week.
26.09.2019 - boundary fences are done, timber flooring is underway and fit off all but complete.
09.010.2019 - external landscaping is underway and the driveway and cross over concrete has been poured.
23.10.2019 - cleaning and painting touch ups underway this week. All but complete!