31.07.2019 - demo is complete, site is cleared and construction is underway.
19.08.2019 - underground drains/plumbing is underway.
30.08.2019 - underground drains/plumbing complete and slab works well underway.
11.09.2019 - steel mesh is in, formwork complete ready to pour the slab weather permitting.
30.09.2019 - slab is complete with the pre-fab frames measured, ordered and due to arrive any day.
09.10.2019 - ground floor framing and steel is underway.
23.10.2019 - first floor framing has started and the ground floor brick work is underway.
07.11.2019 - windows to be installed this week.
14.11.2019 - windows have been installed and the roofing is underway.
28.11.2019 - internal rough-in underway.
12.12.2019 - scaffold going up with external cladding to follow.
19.12.2019 - lower level brickwork is underway.
22.01.2020 - brickwork is done and roof has been installed.
05.02.2020 - sizalation going on ready for external cladding. external lockup edging closer.
19.02.2020 - external cladding is underway.
04.03.2020 - external rendering all but done. Internal rough-in underway.
08.04.2020 - stairs installed and plastering well underway.
23.04.2020 - plastering is complete. Telecommunication lead ins are done. Painting due to commence.
07.05.2020 - painting is underway, driveway and landscaping to commence.
21.05.2020 - tiling to wet areas well underway. Joinery to commence this week.
04.06.2020 - internal painting looking good and joinery underway.
17.06.2020 - exposed aggregate driveways complete. Progressing with joinery and stone for the kitchen.
01.07.2020 - carpet and flooring all but complete.
17.07.2020 - electrical meters are in, gas booked for next week. Internal fit-off underway.
31.07.2020 - internal fit-off all but complete, fencing and landscaping next week.
12.08.2020 - landscaping is on point, we are on the home stretch now.
25.08.2020 - final fit-off, caulking and cleaning ready for handover.