7 Pleasant Road, Hawthorn East

7 pleasant road hawthorn east facade

Finding a place in one of Hawthorn East’s most exclusive and highly sought-after tree-lined pockets will certainly draw the attention of young families as well as those looking to downsize.

These striking residences designed by Award winning Carr Design showcase a considered architectural edge allowing for flexible floorplans and an elegant and sophisticated living experience.

To register your interest contact Andrew or Matt via the details below.

To learn more about Hawthorn East click here

Meet the Builder

Virgon Constructions are award winning builders. Established in 1995, they’re a family owned property construction company. As multi award winning home builders, they strive to continually raise the bar for the home building industry.

Drawing on over 30 years experience and expertise, Virgon ensures they only work with the top professionals in construction, development, design and architecture in Melbourne. As a result everything they touch surpass’s industry standards.

Construction Updates

05.02.2020 - internal painting is all but done and, joinery install is underway. boundary fences are complete.

Previous Updates

22.01.2020 - plastering is done, aircon is in, stairs are in, water proofing and fixing is complete.
19.12.2019 - plaster sheeting is complete, stopping underway. Garages and facade rendered and painted.
12.12.2019 - rough-in complete, insulation and plastering underway.
28.11.2019 - external rendering is complete, rough in all but complete. Fire places installed and final framing almost complete.
14.11.2019 - working on some of the finer detail and specifications. Rendering is underway and joinery measured and ordered.
23.10.2019 - in the final stages of the rough in. Ground floor brickwork is complete.
09.10.2019 - the roof is on and internal plumbing, electrical and aircon rough in underway.
26.09.2019 - framing complete, steel complete, windows installed and double garages nearing lockup.
11.09.2019 - first floor framing all but complete. Windows have been ordered, hebel has been installed.
19.08.2019 - slab poured, framing and steel work underway.
11.07.2019 - retaining walls complete, working on the stormwater connection to council asset, next up forming up the slab.
25.06.2019 - screw pile/bored piers are completed, weather permitting the retaining walls will be done this week so the drainage can be completed.
12.06.2019 - concreter been putting in the bored pier, slab structure underway.
31.05.2019 - construction is well and truly underway, the boys have been tackling the weather to get the drains in ready for the concreter.

Progress Shots

3D Renders

7 pleasant road interior dark
7 pleasant road interior
7 pleasant road

Location