31.05.2019 - construction is well and truly underway, the boys have been tackling the weather to get the drains in ready for the concreter.
12.06.2019 - concreter been putting in the bored pier, slab structure underway.
25.06.2019 - screw pile/bored piers are completed, weather permitting the retaining walls will be done this week so the drainage can be completed.
11.07.2019 - retaining walls complete, working on the stormwater connection to council asset, next up forming up the slab.
19.08.2019 - slab poured, framing and steel work underway.
11.09.2019 - first floor framing all but complete. Windows have been ordered, hebel has been installed.
26.09.2019 - framing complete, steel complete, windows installed and double garages nearing lockup.
09.10.2019 - the roof is on and internal plumbing, electrical and aircon rough in underway.
23.10.2019 - in the final stages of the rough in. Ground floor brickwork is complete.
14.11.2019 - working on some of the finer detail and specifications. Rendering is underway and joinery measured and ordered.
28.11.2019 - external rendering is complete, rough in all but complete. Fire places installed and final framing almost complete.
12.12.2019 - rough-in complete, insulation and plastering underway.
19.12.2019 - plaster sheeting is complete, stopping underway. Garages and facade rendered and painted.
22.01.2020 - plastering is done, aircon is in, stairs are in, water proofing and fixing is complete.
05.02.2020 - internal painting is all but done and, joinery install is underway. boundary fences are complete.
19.02.2020 - feature garage doors are in, electrical fitoff underway.
04.03.2020 - stone installation is done and landscaping is underway.
27.03.2020 - fittings and fixtures being installed. Carpet installed. External feature screens installed.
08.04.2020 - finishing touches inside and landscaping all but done.
23.04.2020 - final caulking, commissioning and cleaning is underway.