7 Pleasant Road, Hawthorn East

7 Pleasant road facade

Finding a place in one of Hawthorn East’s most exclusive and highly sought-after tree-lined pockets will certainly draw the attention of young families as well as those looking to downsize.

These striking townhouses were designed by Award-winning Carr Design showcase a considered architectural edge allowing for flexible floorplans and an elegant and sophisticated living experience.

This project has now been completed, see the image gallery below.

Completed Images

pleasant road living
pleasant road lounge
pleasant road kitchen
pleasant road island
pleasant road master
pleasant road bedroom
pleasant road ensuite
pleasant road bathroom
pleasant road facade
pleasant road rear
pleasant road outlook

Meet the Builder

Virgon Constructions are award-winning builders. Established in 1995, they’re a family-owned property construction company. As multi-award-winning home builders, they strive to continually raise the bar for the home building industry.

Drawing on over 30 years experience and expertise, Virgon ensures they only work with the top professionals in construction, development, design and architecture in Melbourne. As a result, everything they touch surpasses industry standards.

Construction Updates

07.05.2020 - project now complete. Working through final POSD bits and preparing for buyers to move in.

Previous Updates

23.04.2020 - final caulking, commissioning and cleaning is underway.
08.04.2020 - finishing touches inside and landscaping all but done.
27.03.2020 - fittings and fixtures being installed. Carpet installed. External feature screens installed.
04.03.2020 - stone installation is done and landscaping is underway.
19.02.2020 - feature garage doors are in, electrical fitoff underway.
05.02.2020 - internal painting is all but done and, joinery install is underway. boundary fences are complete.
22.01.2020 - plastering is done, aircon is in, stairs are in, water proofing and fixing is complete.
19.12.2019 - plaster sheeting is complete, stopping underway. Garages and facade rendered and painted.
12.12.2019 - rough-in complete, insulation and plastering underway.
28.11.2019 - external rendering is complete, rough in all but complete. Fire places installed and final framing almost complete.
14.11.2019 - working on some of the finer detail and specifications. Rendering is underway and joinery measured and ordered.
23.10.2019 - in the final stages of the rough in. Ground floor brickwork is complete.
09.10.2019 - the roof is on and internal plumbing, electrical and aircon rough in underway.
26.09.2019 - framing complete, steel complete, windows installed and double garages nearing lockup.
11.09.2019 - first floor framing all but complete. Windows have been ordered, hebel has been installed.
19.08.2019 - slab poured, framing and steel work underway.
11.07.2019 - retaining walls complete, working on the stormwater connection to council asset, next up forming up the slab.
25.06.2019 - screw pile/bored piers are completed, weather permitting the retaining walls will be done this week so the drainage can be completed.
12.06.2019 - concreter been putting in the bored pier, slab structure underway.
31.05.2019 - construction is well and truly underway, the boys have been tackling the weather to get the drains in ready for the concreter.

Progress Shots

3D Renders

7 pleasant road
7 pleasant road interior dark
7 pleasant road interior

Location

To learn more about Hawthorn East click here