11.10.2020 - Demolition is complete.
09.11.2020 - In ground plumbing work well underway.
27.11.2020 - Preparations for slab form work and pour to come next.
09.12.2020 - Concrete slab finalised and frame material delivered.
17.12.2020 - Framing underway.
21.01.2021 - Frame and exterior brick wall in progress.
04.02.2021 - Steel frame installation underway, installation of posi struts for the first floor to follow.
18.02.2021 - Sliding door frame and windows delivered stell structure in progress.
04.03.2021 - Brickworks underway.
18.03.2021 - Posi struts installation progressing well.
01.04.2021 - First-floor base floor complete and frame in progress.
15.04.2021 - First-floor frame almost complete and works on roof structure to start soon.
29.04.2021 - Roofing starting this week, services rough-in and external cladding to follow.
13.05.2021 - Fascia gutter installation complete, roof installation close to completion.
27.05.2021 - External cladding on the first-floor and GF roofing in progress.
10.06.2021 - External cladding close to completion and rough-in in progress.
24.06.2021 - External cladding installation complete and electrical rough-in in progress.
08.07.2021 - Insulation complete and plastering well underway.
22.07.2021 - Plastering complete and lower roof flashings almost complete.
06.08.2021 - Skirting and tiling complete, joinery delivered and installation will start next week.
02.09.2021 - Joinery installation in progress.
16.09.2021 - Waiting on flooring delivery to start the installation and finalise joinery.
30.09.2021 - Site has been closed for two weeks (COVID shutdown) back onsite next week.
14.10.2021 - Fit off almost complete and services installations to be finalised shortly.
28.10.2021 - Fit offs and services completed, painting and flooring to be done shortly.
11.11.2021 - Driveway complete and landscape to start in the next few weeks.
25.11.2021 - Landscape in progress and flooring installation complete.
09.12.2021 - Alfresco joinery installation and painting preparation in progress.
20.01.2022 - Construction complete and deflects inspection to be completed next.
03.02.2022 - Defects were rectified and handover is in progress.
17.02.2022 - Handover in progress.