07.07.2022 - Boundary pegs and site set out is scheduled & site cut to follow.
21.07.2022 - Drainage works and rock breaking in progress.
05.08.2022 - Drainage works completed.
23.08.2022 - Footings, reinforcement and formworks completed onsite.
2.09.2022 - Slabs are poured and framing has commenced.
15.09.2022 - Framing to continue and garage brick laying to start.
29.09.2022 - Timber frame & brick garages in progress and steel installation to commence.
13.10.2022 - Brick garages done, brick clean and steel installation to start soon.
27.10.2022 - Brick cleaning is done and awaiting steel delivery for installation.
10.11.2022 - Steel installation is in progress.
24.11.2022 - First floor framing in progress.
08.12.2022 - Roof framing is in progress and roof cover to follow.
20.01.2023 - Framing completed and roof covers in progress.
02.02.2023 - Roof covers are done on the first floor and service rough-ins started.
16.02.2023 - Plumber rough-ins nearing completions and gutters and fascia to follow.
02.03.2023 - Fascia, roof gutters & ground floor roofs nearing completion and eaves to start.
16.03.2023 - Cladding install to Units 3 & 4 is in progress with install to Units 1 & 2 to follow.
30.03.2023 - Wall wrapping done and cladding for units 1 & 2 in progress.
13.04.2023 - Lower cladding nearing completion.
27.04.2023 - Upper Cladding to continue.
11.05.2023 - Upper floor cladding to continue, internal lockup & render to start.
08.06.2023 - Lockup is completed.
22.06.2023 - Rough-ins in progress and external painting & insulation in progress.
06.07.2023 - Ceiling battens done and Plastering is in progress.
20.07.2023 - Plastering completed and fixing carpenter to start.
03.08.2023 - Carpenter fix in progress.
17.08.2023 - Carpentry fix completed and cabinetry installation to start.
31.08.2023 - Cabinetry installation & painting in progress.
14.09.2023 - Electrical undergrounds, downpipes & rain-heads completed.
12.10.2023 - Waterproofing nearing completion and tiling to start.
26.10.2023 - Commencement of joinery and stone installation soon.
09.11.2023 - Tiling is in progress.
23.11.2023 - Stone installation complete.
07.12.2023 - Plumbing and electrical fit off to start and decking to follow.
18.01.2024 - Driveway prep done, carpentry & internal glazing fit off to start.
01.02.2024 - External rendering works and unit 1 decking to start.
15.02.2024 - Flooring is scheduled to go in this week.
29.02.2024 - Flooring is underway.
14.03.2024 - Flooring is complete.
28.03.2024 - Landscaping preparation works in progress.
11.04.2024 - continuation of previous fortnights work.
09.05.2024 - Internal fencing completed and driveway prep in progress.
23.05.2024 - Driveways are poured and soft landscaping in progress.
06.06.2024 - Fencing is in progress and internal glazing to commence.
21.06.2024 - Fencing has been completed and landscaping to commence.
04.07.2024 - Fences have been painted and shed construction has commenced.
18.07.2024 - Electricity meters are installed.