37 Mount Street, Altona

4
3
2
25 minutes
to CBD

Mount street Altona is an exciting project that we gained town planning approval for two substantial dwellings of approx. 30sqs each with both sitting on approx. 400sqm of land each, it’s a site we are extremely excited about.

Demolition is now complete with construction anticipated to begin late October.

Interior Design

Interior design for the project is by Dani Wales and Ashlee Moyal over at Red Door Project, “the overall aesthetic will comprise of warm grey tones and walnut timbers explored through joinery whilst ensuring a restrained yet considered Modern Australian aesthetic is achieved” Dani Wales.

We simply can’t wait to see how it all comes together.

Sales Enquiries

For sales enquiries please contact either Tony or Gus using the details below.

Click here to view the property listing on RealEstate.com

3D Renders

Construction Updates

18.07.2019 - the insulation is all in, the plastering is underway and the top floor external works are complete.

Previous Updates

11.07.2019 - brickwork complete, rough in complete and plastering to come.
24.06.2019 - the aircon rough in is complete, electrical rough is about to kick off and second floor brickwork is all but complete.
12.06.2019 - roofing and guttering complete, second floor brickwork underway.
06.05.2019 - first floor flooring is down and the framing is underway.
24.04.2019 - the posi struts are installed and the first floor flooring has been delivered ready to be installed.
12.04.2019 - the windows are in and the ground floor brickwork is underway.
01.04.2019 - ground floor steel has been installed. Chippies back onsite installing windows tomorrow.
20.03.2019 - garages have been bricked up, first floor steel about to go in. Trusses have been ordered.
05.03.2019 - first floor frame is done, roof trusses have been ordered.
21.02.2019 - framers are onsite and the first floor framing is underway.
15.02.2019 - the slab is down, the framers are locked in for next week.
06.02.2019 - slab preparation all but complete, reo and boxing to follow with the slab booked to be poured next week.
20.12.2018 - construction has started on site, the drains are in and the slab is booked for first cab off the rank in the new year. Here we go!
12.12.2018 - demolition is complete and construction is about to start. Aiming for the drains to be done this side of Christmas with the slab to be poured first thing in the new year.

Progress Images

Click on the gallery below to view the latest images from out on site.

Floor Plans

Click the gallery below to view the plans full screen.

Meet The Builder

The builder for this projects is Renza Homes. Click play on the video below to meet Shane Fiorenza, Renza Homes’s managing director.

Property Brochure

Click below to view the 37 Mount Street property brochure.

Location

To learn more about Altona click here.